Hainan Southwest Power Station 海南西南部电厂 | |
---|---|
Location | Ledong Li Autonomous County, Hainan Province [1] |
Purpose | Power |
Construction began | June 2014 [2] |
Construction cost | ¥3.784 billion [3] |
Hainan Southwest Power Station ( Chinese: 海南西南部电厂 [4]), also known as Hainan Southwest Power Plant, [5] is a Chinese thermal power plant [6] located in Foluo Town (佛罗镇) on the west coast of Ledong Li Autonomous County, Hainan Province, [7] with a total investment of 3.784 billion yuan. [8]
Hainan Southwest Power Station was approved by the National Development and Reform Commission in May 2014, and its construction started on June 30, 2014. [9]
In July 2015, the generating station started trial operation. [10] The No. 2 unit of the Southwest Power Plant was officially put into operation on October 16, marking the official launch of all units of the power plant into operation. [11]
{{
cite book}}
: |work=
ignored (
help)
Hainan Southwest Power Station 海南西南部电厂 | |
---|---|
Location | Ledong Li Autonomous County, Hainan Province [1] |
Purpose | Power |
Construction began | June 2014 [2] |
Construction cost | ¥3.784 billion [3] |
Hainan Southwest Power Station ( Chinese: 海南西南部电厂 [4]), also known as Hainan Southwest Power Plant, [5] is a Chinese thermal power plant [6] located in Foluo Town (佛罗镇) on the west coast of Ledong Li Autonomous County, Hainan Province, [7] with a total investment of 3.784 billion yuan. [8]
Hainan Southwest Power Station was approved by the National Development and Reform Commission in May 2014, and its construction started on June 30, 2014. [9]
In July 2015, the generating station started trial operation. [10] The No. 2 unit of the Southwest Power Plant was officially put into operation on October 16, marking the official launch of all units of the power plant into operation. [11]
{{