Eastern HVDC and Eastern HVDC projects are the names used by Ofgem for two planned HVDC submarine power cables from the East coast of Scotland to Northeast England to strengthen the National Grid. The two links combined will deliver 4 GW of renewable energy from Scottish wind farms to England.
Ofgem state that "At an estimated cost of £3.4 billion for the two links, the Eastern HVDC projects would be the largest electricity transmission investment project in the recent history of Great Britain." [1]
In July 2022, Ofgem published its conditional decision on the Final needs case for the Eastern HVDC project, confirming its choice of two separate HVDC links, each rated at 2 GW. [1]
Ofgem approved the schemes as part of its Accelerated Strategic Transmission Investment Framework. [2]
In December 2022, the connection received approval from the UK energy regulator Ofgem. [2] [3] As of July 2021, construction was expected to start in 2023, with the construction phase complete in 2027. [4]
SEGL1 will run from Torness in Southeast Scotland to Hawthorn Pit substation in Northeast England. [5] Landfall in England will be to the North of Seaham, on the Durham Coast. [4]
The cable will carry 2 GW. [3] The DC voltage will be +/-525 kV, using voltage source converter (VSC) technology, carried on cross-linked polyethylene (XLPE) cables, with a fall back option of mass impregnated (MI) cables. [1]
The investment required is £1.294 billion. [1]
SEGL1 is being developed by Scottish Power Transmission plc (SPT) and National Grid Electricity Transmission plc (National Grid). [5]
Contracts to construct the cable were finalised in February 2024, and work is scheduled to commence after final approvals from OfGEM. [6] [7]
In December 2022, the connection received approval from the UK energy regulator Ofgem. [2]
In December 2022, the project was in the "early development" stage. [5]
In December 2022, early enabing works were expected in 2024, with the main construction phase starting in 2025. Target date for energisation was 2029. [3]
The cable will run from Sandford Bay, at Peterhead in Scotland, to the Drax Power Station in Yorkshire, England. The northern converter station will be next to the existing power station at Peterhead. [3] [5] The subsea portion of the cable will be approximately 440 km (270 mi) long, from the Aberdeenshire coast to the East Riding of Yorkshire. [8]
The cable will carry 2 GW. [3] The DC voltage will be +/-525 kV, using Voltage Source converter (VSC) technology, carried on Cross-linked polyethylene (XLPE) cables, with a fall back option of mass impregnated (MI) cables. [1]
The investment required is £2.1 billion. It is needed to reinforce the National Grid, to "alleviate existing and future constraints on the electricity transmission network", and support new renewable electricity generation. [3]
EGL2 is a joint venture between SSEN Transmission and National Grid Electricity Transmission (NGET). [3]
The main contractors are Prysmian, Hitachi Energy, and BAM. [6]
Eastern HVDC and Eastern HVDC projects are the names used by Ofgem for two planned HVDC submarine power cables from the East coast of Scotland to Northeast England to strengthen the National Grid. The two links combined will deliver 4 GW of renewable energy from Scottish wind farms to England.
Ofgem state that "At an estimated cost of £3.4 billion for the two links, the Eastern HVDC projects would be the largest electricity transmission investment project in the recent history of Great Britain." [1]
In July 2022, Ofgem published its conditional decision on the Final needs case for the Eastern HVDC project, confirming its choice of two separate HVDC links, each rated at 2 GW. [1]
Ofgem approved the schemes as part of its Accelerated Strategic Transmission Investment Framework. [2]
In December 2022, the connection received approval from the UK energy regulator Ofgem. [2] [3] As of July 2021, construction was expected to start in 2023, with the construction phase complete in 2027. [4]
SEGL1 will run from Torness in Southeast Scotland to Hawthorn Pit substation in Northeast England. [5] Landfall in England will be to the North of Seaham, on the Durham Coast. [4]
The cable will carry 2 GW. [3] The DC voltage will be +/-525 kV, using voltage source converter (VSC) technology, carried on cross-linked polyethylene (XLPE) cables, with a fall back option of mass impregnated (MI) cables. [1]
The investment required is £1.294 billion. [1]
SEGL1 is being developed by Scottish Power Transmission plc (SPT) and National Grid Electricity Transmission plc (National Grid). [5]
Contracts to construct the cable were finalised in February 2024, and work is scheduled to commence after final approvals from OfGEM. [6] [7]
In December 2022, the connection received approval from the UK energy regulator Ofgem. [2]
In December 2022, the project was in the "early development" stage. [5]
In December 2022, early enabing works were expected in 2024, with the main construction phase starting in 2025. Target date for energisation was 2029. [3]
The cable will run from Sandford Bay, at Peterhead in Scotland, to the Drax Power Station in Yorkshire, England. The northern converter station will be next to the existing power station at Peterhead. [3] [5] The subsea portion of the cable will be approximately 440 km (270 mi) long, from the Aberdeenshire coast to the East Riding of Yorkshire. [8]
The cable will carry 2 GW. [3] The DC voltage will be +/-525 kV, using Voltage Source converter (VSC) technology, carried on Cross-linked polyethylene (XLPE) cables, with a fall back option of mass impregnated (MI) cables. [1]
The investment required is £2.1 billion. It is needed to reinforce the National Grid, to "alleviate existing and future constraints on the electricity transmission network", and support new renewable electricity generation. [3]
EGL2 is a joint venture between SSEN Transmission and National Grid Electricity Transmission (NGET). [3]
The main contractors are Prysmian, Hitachi Energy, and BAM. [6]